"Van Vleck ISD board hears bond updates" by: Jessica Shepard

   Van Vleck ISD trustees heard several bond construction updates during their regular meeting March 22.
   “The middle school is moving along on schedule,” said PBK Associate Architect Elizabeth Giusti.
   “Tiling is at about 85% complete and they’ll be doing more flooring soon.”
   Giusti added that the drywall was mostly installed and the painting was ongoing.
   “Light fixtures are also at about 60% and the new gym flooring is being done right now,” she said.
   “The elementary is nearly complete along with punch-list items and everything is moving really well in the high school.”